Percentage change in total deployment costs using the estimated minimum and maximum cost price per category, for the scenarios ‘outplacement of adult oysters on concrete structures’ and ‘outplacement of spat on shell’. Bold numbers indicate large increases or decreases in total deployment costs.

Adults on concrete

Category Type Min price Max
price
Unit Nr of
units
% change in costs min
price
% change in costs max
price
Material Concrete structure € 70.2 € 348.2 €/m2 400 m2 −5.2 25.9
Glue € 0.15 € 0.35 €/oyster 12,000 oysters −0.5 0.2
Labor AIS protocol € 90 € 210 €/hour 300 h −5.0 5.0
Preparations & outplacement € 90 € 210 €/hour 1,280 h −21.5 21.5
Shipping Outplacement € 23,500 €/days 2.5 d 0.0 16.4
Transport Concrete structure € 1,375 € 1,925 €/days 1 d 0.0 0.2
Oysters Acquiring € 0.52 € 3.83 €/oyster 12,000 oysters −1.1 10.0
Spat on shell

Category Type Min price Max
price
Unit Nr of
units
% change in costs min
price
% change in costs max
price
Material Settled spat € 20,000 € 45,000 €/unit 1 −9.7 14.6
Labor AIS protocol € 90 € 120 €/hour 150 h −8.8 0.2
Preparations & outplacement € 90 € 210 €/hour 153 h −8.9 5.0
Shipping Outplacement € 23,500 €/days 1 d 0 22.9
Transport Settled spat € 2,325 € 5,425 €/days 1 d −1.5 1.5

Current usage metrics show cumulative count of Article Views (full-text article views including HTML views, PDF and ePub downloads, according to the available data) and Abstracts Views on Vision4Press platform.

Data correspond to usage on the plateform after 2015. The current usage metrics is available 48-96 hours after online publication and is updated daily on week days.

Initial download of the metrics may take a while.